Reflex BIM -alustamme antaa MEP-suunnittelijoille ja -asentajille nopean pääsyn räätälöityihin BIM-objekteihin Autodesk Revitissä, IFC:ssä ja muissa muodoissa.
Toimeksianto asiakaspalvelulle
Reflex Solutions Pro
PROSINUS® X
Asiakirjat ja videot
BIM@Reflex
Tietoja Reflexistä
Tietoja meistä
Miten aloitimme, mikä saa meidät jatkamaan ja mikä on tavoitteemme?
Messut ja tapahtumat
Tutustumme mielellämme sinuun eri tapahtumissa, joille osallistumme.
reflexGroup
reflexGroup on Winkelmann Groupiin kuuluva liiketoimintayksikkö.
Tietoja Reflex Winkelmann GmbH
Tulevat messut ja tapahtumat
Tietoja reflexGroup
Alue/kieli
Project
Heating Plant
User: Gateshead Council
local heating network
heating
separation, pressure maintenance, skid
Performance parameter
System volume: appr. 660.000 Liter
Power: 22,5 MW
Task
Reflex was commissioned to create a robust, customized solution to facilitate a district energy network and Combined Heat & Power (CHP) Centre in the Gateshead Quays area. Due to on site space constraints, the specification demanded a great deal of flexibility in the pressurisation maintenance station manufacturers approach. The task was to create a solution which could not only accomodate the system heat load but to also satisfy the space restictions within the plant room
Product solution
1 x Variomat Giga GS 1.1, control unit
1 x Variomat Giga hydraulic module
1 x 8,000 litre Reflex basic vessel
3 x 8,000 litre Reflex secondary vessels
1 x extension module
4 x diaphragm rupture detector
1 x Servitec special system 90-4
1 x skid base incorporating all but the 8,000 litre vessels
1 of 1
Achieved goals
Creating a customized solution including a packaged pressure maintenance station/ vacuum degasser and specific vessels resulted in lower installation costs and a more efficient solution. Residents in the area will be able to enjoy reduced exposure to Carbon Reduction Commitment (CRC) and Climate Change Levy.
On-going heating plant maintenance, servicing and replacement costs will be reduced
An estimated 400 homes and 6 public buildings will benefit with capacity to significantly increase the network in the future.