Reflex BIM -alustamme antaa MEP-suunnittelijoille ja -asentajille nopean pääsyn räätälöityihin BIM-objekteihin Autodesk Revitissä, IFC:ssä ja muissa muodoissa.
Toimeksianto asiakaspalvelulle
Reflex Solutions Pro
PROSINUS® X
Asiakirjat ja videot
BIM@Reflex
Tietoja Reflexistä
Tietoja meistä
Miten aloitimme, mikä saa meidät jatkamaan ja mikä on tavoitteemme?
Messut ja tapahtumat
Tutustumme mielellämme sinuun eri tapahtumissa, joille osallistumme.
Winkelmann Building+Industry
Winkelmann Building+Industry on Winkelmann Groupiin kuuluva liiketoimintayksikkö.
Tietoja Reflex Winkelmann GmbH
Tulevat messut ja tapahtumat
Tietoja Winkelmann Building+Industry
Alue/kieli
Project
Power self-sufficiency at the site "Schmalbachstrasse" of Winkelmann Powertrain Components GmbH + Co. KG
Commissioned in: January 2019
factory
heating
separation, pressure maintenance, make-up, water storage technology
Performance parameter
6 CHPs from MTU Onsite Energy GmbH
Furnace capacity: 3,649 kW, Electrical capacity: 1,554 kW, Thermal capacity: 1,600 kW (per CHP in each case)
2 x flywheel storage for frequency and voltage stability
Lithium battery storage with 1,000 kW capacity for weak load periods
Task
Customised production of three buffer tanks with a water capacity of 44 m³ each, and installation of the tanks on the roof
Provision of a pre-fabricated skid solution for pressure maintenance, degassing and make-up
Product solution
3 x buffer tanks 44,000 litres, 100°C, 6 bar, 200 mm insulation Skid solution– Pressure maintenance, degassing, make-up – consisting of:
2 x Variomat VS 2-2/60 control units and 2 x Variomat VG 5000 primary vessels
1 x Reflex V 3000 auxiliary vesse
1 x Servitec 60 vacuum spray-tube degassing
1 of 1
Achieved goals
On 1 January 2019, Winkelmann Group disconnected one of its sites from the public grid. Since then, the site has been fully self-powered
Within the overall strategy, the Reflex buffer tanks serve as hydraulic separators, buffering heat, e.g. at the weekend
The Reflex skid solution guarantees reliable pressure maintenance, degassing and makeup and is controlled by the central building management system.